Multiple Choice Questions on Civil Engineering | Objective Questions | Civil Engineering Quiz | MCQ
1 >>Mile Stone charts were invented in the year of ?
2 >>Frederick W. Taylor introduced a system of working known as ?
3 >>Pick up the PERT event from the following: ?
Download
4 >>If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good ?
6 >>The performance of a specific task in CPM, is known ?
7 >>A Milestone chart ?
8 >>Completion of an activity on CPM network diagram, is generally known ?
9 >>A dummy activity ?
10 >>Military organisation is known as ?
11 >>Pick up the incorrect statement from the following: ?
12 >>Various activities of a project, are shown on bar charts by ?
13 >>Time and progress chart of a construction, is also known as ?
14 >>Critical Path Net Work helps an engineer ?
15 >>The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as ?
16 >>The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as ?
17 >>Henry Gantt developed Bar charts for planning and scheduling of projects in ?
18 >>The most popular type of organisation used for Civil Engineering Constructions, is ?
19 >>The difference between the time availto do a job and the time required to do the job, is known as ?
20 >>The object of technical planning, is ?
- (A) 1910
- (B) 1920
- (C) 1930
- (D) 1940
- (A) line organisation
- (B) line and staff organisation
- (C) functional organisation
- (D) effective organization
- (A) Digging of foundation started
- (B) Digging of foundation completed
- (C) Laying of concrete started
- (D) All the above
Download
4 >>If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good ?
- (A) EF = ES + D
- (B) LS = LF D
- (C) LF = LS + D
- (D) all the above
5 >>Final technical authority of a project lies with ?
- (A) Assistant Engineer
- (B) Executive Engineer
- (C) Superintending Engineer
- (D) Chief Engineer
- (A) Dummy
- (B) Event
- (C) Activity
- (D) Contract
- (A) shows the interdependencies of various jobs
- (B) depicts the delay of jobs, if any
- (C) points outgoing ahead of schedule of jobs, if any
- (D) none of these
- (A) Event
- (B) Node
- (C) Connector
- (D) All the above
- (A) is artificially introduced
- (B) is represented by a dotted line
- (C) does not consume time
- (D) all the above
- (A) line organisation
- (B) line and staff organisation
- (C) functional organisation
- (D) none of these
11 >>Pick up the incorrect statement from the following: ?
- (A) The activity is the time consuming part of a project
- (B) The beginning and end of a job, are called events
- (C) The activity which consumes maximum time, is called a node
- (D) Logically and sequentially connected activities and events form a network
12 >>Various activities of a project, are shown on bar charts by ?
- (A) vertical lines
- (B) horizontal lines
- (C) dots
- (D) crosses
- (A) Bar chart
- (B) Gantt chart
- (C) Modified Mile stone chart
- (D) All the above
- (A) to concentrate his attention on critical activities
- (B) to divert the resources from noncritical advanced activities to critical activities
- (C) to be cautious for avoiding any delay in the critical activities to avoid delay of the whole project
- (D) all the above
- (A) duration
- (B) total flat
- (C) free float
- (D) interfering float
- (A) event
- (B) free float
- (C) dummy
- (D) constant
- (A) 1880
- (B) 1900
- (C) 1920
- (D) 1940
- (A) line organisation
- (B) line and staff organisation
- (C) functional organisation
- (D) effective organization
- (A) event
- (B) float
- (C) duration
- (D) constraint
- (A) preparation of specifications
- (B) preparation of estimates
- (C) initiating the procurement action of resources
- (D) all the above